Construction Update

MAY 2026

IMG_20260526_155503.jpg

Tower 1  

Structure work Complete.

Plumbing Internal: 95% complete

Plumbing External: 90% complete

Fire Fighting: 95% complete

Tile work: 90% complete

Marble Flooring: 95% complete

Door Frames: Complete

PoP work: 95% complete

HVAC work: 90% complete

IMG_20260526_155625.jpg

Tower 2  

Structure work Complete.

Plumbing Internal: Complete

Plumbing External: Complete

Fire Fighting: Complete

Tile work: 90% complete

Marble Flooring: Complete

Door Frames: Complete

PoP work: 95% complete

HVAC work: 90% complete

IMG_20260521_161819.jpg

Tower 3  

Structure work Complete.

Plumbing Internal: Complete

Plumbing External: Complete

Fire Fighting: Complete

Tile work: 95% complete

Marble Flooring: Complete

Door Frames: Complete

PoP work: Complete

HVAC work: Complete

IMG_20260521_162124.jpg

Tower 4  

Structure work at 25th floor in progress.

IMG_20260421_160405.jpg
IMG_20260521_161517.jpg

Tower 5  

Structure work Complete.

Plumbing Internal: 75% complete

Plumbing External: 75% complete

Fire Fighting: 80% complete

Tile work: 60% complete

Marble Flooring: 95% complete

Door Frames: 60% complete

PoP work: 90% complete

HVAC work: 60% complete

IMG_20240527_180733.jpg

Tower 6  

Structure work Complete.

Plumbing Internal: 95% complete

Plumbing External: 90% complete

Fire Fighting: 95% complete

Tile work: 90% complete

Marble Flooring: Complete

Door Frames: 70% complete

PoP work: 95% complete

HVAC work: 90% complete

IMG_20260521_161506.jpg
IMG_20240527_180157.jpg
IMG_20260521_155244.jpg

Tower 7  

Structure work Complete.

Plumbing Internal: 95% complete

Plumbing External: 95% complete

Fire Fighting: 85% complete

Tile work: 80% complete

Marble Flooring: 95% complete

Door Frames: 75% complete

PoP work: 90% complete

HVAC work: 70% complete

Tower 8  

Structure work at 22nd floor in progress.

Tower 9

Structure work at 18th floor in progress.

IMG_20260521_155231.jpg
IMG_20240527_180157.jpg
IMG_20260521_154918.jpg

Tower 10

Structure work at 7th floor in progress.

RERA REGN NO. - 29 OF 2022

Depictions are for illustrative purposes and should not be considered as actual representations. Final design and specifications may differ.