Construction Update
SEPTEMBER 2025

Tower 1
Structure work Complete.
Plumbing Internal: 70% complete
Plumbing External: 50% complete
Fire Fighting: 45% complete
Tile work: 45% complete
Marble Flooring: 50% complete
Door Frames: 70% complete
PoP work: 60% complete
HVAC work: 45% complete

Tower 2
Structure work Complete.
Plumbing Internal: 90% complete
Plumbing External: 65% complete
Fire Fighting: 60% complete
Tile work: 50% complete
Marble Flooring: 70% complete
Door Frames: 90% complete
PoP work: 60% complete
HVAC work: 60% complete

Tower 3
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 90% complete
Fire Fighting: Complete
Tile work: 85% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 90% complete
HVAC work: 90% complete

Tower 4
Structure work at 10th floor in progress.
Tower 5
Structure work Complete, Finishing work started.


Tower 6
Structure work Complete.
Plumbing Internal: 40% complete
Plumbing External: 10% complete
Fire Fighting: 30% complete
Tile work: 30% complete
Marble Flooring: 50% complete
Door Frames: 10% complete
PoP work: 60% complete
HVAC work: 20% complete

Tower 7
Structure work Complete.
Plumbing Internal: 60% complete
Plumbing External: 30% complete
Fire Fighting: Started
Tile work: 10% complete
Marble Flooring: 30% complete
Door Frames: 10% complete
PoP work: 50% complete
HVAC work: 10% complete



Tower 8
Structure work at 7th floor in progress.
Tower 9
Structure work at 3rd floor in progress.
Tower 10
Structure work at Lower Ground floor in progress.