Construction Update

JANUARY 2024

T-1,2.jpg
T-3.jpg

Tower 1 Structure work at 21st floor in progress

Tower 2 Structure work at 26th floor in progress

Tower 3 Structure Complete, Finishing work in progress

T-4.jpg

Tower 4 Structure work at 2nd Basement in progress

T-5.jpg

Tower 5 Structure work at 14th floor in progress

T-6,7.jpeg
T-6,7.jpeg

Tower 6 Structure work at 15th floor in progress

Tower 7 Structure work at 17th floor in progress

T-5 6 7.jpg

Tower 8 Structure work at 3rd Basement in progress

Tower 9 Raft Foundation work in progress

T-8 i.jpeg
T-8.jpg
T-10.jpeg

Tower 10 Raft Foundation work in progress