
Construction Update
MARCH 2026

Tower 1
Structure work Complete.
Plumbing Internal: 90% complete
Plumbing External: 85% complete
Fire Fighting: 90% complete
Tile work: 80% complete
Marble Flooring: 90% complete
Door Frames: 90% complete
PoP work: 90% complete
HVAC work: 85% complete

Tower 2
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 90% complete
Fire Fighting: Complete
Tile work: 85% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 90% complete
HVAC work: 90% complete

Tower 3
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: Complete
Fire Fighting: Complete
Tile work: 90% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 95% complete
HVAC work: Complete

Tower 4
Structure work at 21st floor in progress.


Tower 5
Structure work Complete.
Plumbing Internal: 70% complete
Plumbing External: 60% complete
Fire Fighting: 70% complete
Tile work: 50% complete
Marble Flooring: 90% complete
Door Frames: 50% complete
PoP work: 85% complete
HVAC work: 50% complete

Tower 6
Structure work Complete.
Plumbing Internal: 90% complete
Plumbing External: 70% complete
Fire Fighting: 80% complete
Tile work: 85% complete
Marble Flooring: 90% complete
Door Frames: 60% complete
PoP work: 85% complete
HVAC work: 80% complete



Tower 7
Structure work Complete.
Plumbing Internal: 90% complete
Plumbing External: 80% complete
Fire Fighting: 75% complete
Tile work: 60% complete
Marble Flooring: 75% complete
Door Frames: 70% complete
PoP work: 80% complete
HVAC work: 50% complete
Tower 8
Structure work at 18th floor in progress.
Tower 9
Structure work at 13th floor in progress.



Tower 10
Structure work at 4th floor in progress.
