Construction Update
AUGUST 2025

Tower 1
Structure work Complete.
Plumbing Internal: 60% complete
Plumbing External: 50% complete
Fire Fighting: 30% complete
Tile work: 45% complete
Marble Flooring: 30% complete
Door Frames: 50% complete
PoP work: 50% complete
HVAC work: 35% complete

Tower 2
Structure work Complete.
Plumbing Internal: 85% complete
Plumbing External: 55% complete
Fire Fighting: 50% complete
Tile work: 50% complete
Marble Flooring: 50% complete
Door Frames: 80% complete
PoP work: 55% complete
HVAC work: 50% complete

Tower 3
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 90% complete
Fire Fighting: Complete
Tile work: 80% complete
Marble Flooring: 90% complete
Door Frames: 90% complete
PoP work: 90% complete
HVAC work: 90% complete

Tower 4
Structure work at 8th floor in progress.
Tower 5
Structure work Complete.


Tower 6
Structure work Complete.
Plumbing Internal: 30% complete
Plumbing External: Started
Fire Fighting: 20% complete
Tile work: 20% complete
Marble Flooring: 40% complete
Door Frames: Started
PoP work: 60% complete
HVAC work: 15% complete

Tower 7
Structure work Complete.
Plumbing Internal: 45% complete
Plumbing External: 20% complete
Fire Fighting: Started
Tile work: Started
Marble Flooring: 20% complete
Door Frames: Started
PoP work: 50% complete
HVAC work: 10% complete



Tower 8
Structure work at 5th floor in progress.
Tower 9
Structure work at 2nd floor in progress.
Tower 10
Structure work at Lower Ground floor in progress.