Construction Update
JULY 2026

Tower 1
Structure work Complete.
Plumbing Internal: 95% complete
Plumbing External: 95% complete
Fire Fighting: 95% complete
Tile work: 90% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 95% complete
HVAC work: 95% complete

Tower 2
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: Complete
Fire Fighting: Complete
Tile work: 95% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 95% complete
HVAC work: Complete

Tower 3
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: Complete
Fire Fighting: Complete
Tile work: Complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: Complete
HVAC work: Complete

Tower 4
Structure work at 29th floor in progress.


Tower 5
Structure work Complete.
Plumbing Internal: 85% complete
Plumbing External: 85% complete
Fire Fighting: 95% complete
Tile work: 80% complete
Marble Flooring: Complete
Door Frames: 80% complete
PoP work: Complete
HVAC work: 80% complete

Tower 6
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 95% complete
Fire Fighting: Complete
Tile work: 95% complete
Marble Flooring: Complete
Door Frames: 80% complete
PoP work: Complete
HVAC work: Complete



Tower 7
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 95% complete
Fire Fighting: 95% complete
Tile work: 90% complete
Marble Flooring: Complete
Door Frames: 85% complete
PoP work: Complete
HVAC work: 90% complete
Tower 8
Structure work at 25th floor in progress.
Tower 9
Structure work at 20th floor in progress.



Tower 10
Structure work at 9th floor in progress.