Construction Update
APRIL 2024


Tower 1 Structure work at 26th floor in progress
Tower 2 Structure work at 31st floor in progress
Tower 3 Structure Complete, Finishing work in progress

Tower 4 Structure work at 1st Basement in progress

Tower 5 Structure work at 21st floor in progress


Tower 6 Structure work at 24th floor in progress
Tower 7 Structure work at 25th floor in progress

Tower 8 Structure work at 3rd Basement in progress



Tower 9 Structure work at 3rd Basement in progress
Tower 10 Structure work at 3rd Basement in progress