
Construction Update
APRIL 2025

Tower 1
Structure work at 39th floor in progress.
Plumbing Internal: 20% complete
Plumbing External: 20% complete
Fire Fighting: Started
Tile work: Started
Marble Flooring: Started
Door Frames: Started
PoP work: Started
HVAC work: Started

Tower 2
Structure work Complete.
Plumbing Internal: 40% complete
Plumbing External: 25% complete
Fire Fighting: Started
Tile work: Started
Marble Flooring: 10% complete
Door Frames: 40% complete
PoP work: 25% complete
HVAC work: 20% complete

Tower 3
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 50% complete
Fire Fighting: 75% complete
Tile work: 40% complete
Marble Flooring: 90% complete
Door Frames: 70% complete
PoP work: 70% complete
HVAC work: 70% complete

Tower 4
Structure work at 2nd floor in progress.
Tower 5
Structure work at 36th floor in progress.


Tower 6
Structure work Complete.
Finishing work started.
Tower 7
Structure work Complete.
Finishing work started.

Tower 8
Structure work at 1st floor in progress.



Tower 9
Structure work at U. Ground floor in progress.
Tower 10
Structure work at Basement-1 in progress.