Construction Update

APRIL 2025

IMG_20250429_171259.jpg

Tower 1  

Structure work at 39th floor in progress.

Plumbing Internal: 20% complete

Plumbing External: 20% complete

Fire Fighting: Started

Tile work: Started

Marble Flooring: Started

Door Frames: Started

PoP work: Started

HVAC work: Started

IMG_20250429_141226.jpg

Tower 2  

Structure work Complete.

Plumbing Internal: 40% complete

Plumbing External: 25% complete

Fire Fighting: Started

Tile work: Started

Marble Flooring: 10% complete

Door Frames: 40% complete

PoP work: 25% complete

HVAC work: 20% complete

IMG_20250429_141143.jpg

Tower 3  

Structure work Complete.

Plumbing Internal: Complete

Plumbing External: 50% complete

Fire Fighting: 75% complete

Tile work: 40% complete

Marble Flooring: 90% complete

Door Frames: 70% complete

PoP work: 70% complete

HVAC work: 70% complete

IMG_20250429_140911.jpg

Tower 4  

Structure work at 2nd floor in progress.

Tower 5

Structure work at 36th floor in progress.

IMG_20241231_114509_edited.jpg
IMG_20250429_171144.jpg

Tower 6 

Structure work Complete.

Finishing work started.

Tower 7 

Structure work Complete.

Finishing work started.

IMG_20240527_180733.jpg

Tower 8  

Structure work at 1st floor in progress.

IMG_20250429_142153.jpg
IMG_20240527_180157.jpg
IMG_20250429_141812.jpg

Tower 9

Structure work at U. Ground floor in progress.

Tower 10

Structure work at Basement-1 in progress.