Construction Update

JUNE 2026

IMG_20260526_153326.jpg

Tower 1  

Structure work Complete.

Plumbing Internal: 95% complete

Plumbing External: 90% complete

Fire Fighting: 95% complete

Tile work: 90% complete

Marble Flooring: Complete

Door Frames: Complete

PoP work: 95% complete

HVAC work: 95% complete

IMG_20260606_101601.jpg

Tower 2  

Structure work Complete.

Plumbing Internal: Complete

Plumbing External: Complete

Fire Fighting: Complete

Tile work: 95% complete

Marble Flooring: Complete

Door Frames: Complete

PoP work: 95% complete

HVAC work: Complete

IMG_20260606_101516.jpg

Tower 3  

Structure work Complete.

Plumbing Internal: Complete

Plumbing External: Complete

Fire Fighting: Complete

Tile work: 95% complete

Marble Flooring: Complete

Door Frames: Complete

PoP work: Complete

HVAC work: Complete

IMG_20260606_101412.jpg

Tower 4  

Structure work at 27th floor in progress.

IMG_20260421_160405.jpg
IMG_20260521_155306.jpg

Tower 5  

Structure work Complete.

Plumbing Internal: 80% complete

Plumbing External: 80% complete

Fire Fighting: 90% complete

Tile work: 70% complete

Marble Flooring: 95% complete

Door Frames: 70% complete

PoP work: 90% complete

HVAC work: 70% complete

IMG_20240527_180733.jpg

Tower 6  

Structure work Complete.

Plumbing Internal: 95% complete

Plumbing External: 95% complete

Fire Fighting: 95% complete

Tile work: 90% complete

Marble Flooring: Complete

Door Frames: 80% complete

PoP work: 95% complete

HVAC work: 95% complete

IMG_20260616_112646.jpg
IMG_20240527_180157.jpg
IMG_20260606_100813.jpg

Tower 7  

Structure work Complete.

Plumbing Internal: 95% complete

Plumbing External: 95% complete

Fire Fighting: 90% complete

Tile work: 85% complete

Marble Flooring: Complete

Door Frames: 80% complete

PoP work: 95% complete

HVAC work: 85% complete

Tower 8  

Structure work at 24th floor in progress.

Tower 9

Structure work at 19th floor in progress.

IMG_20260606_100515.jpg
IMG_20240527_180157.jpg
WhatsApp Image 2026-06-24 at 8.52.04 AM.jpeg

Tower 10

Structure work at 8th floor in progress.