Construction Update
January 2023

Tower-1: 8th Floor roof slab casted, 9th Floor structure work in progress.

Tower-2: 6th Floor roof slab casted, 7th Floor structure work in progress.


Tower-3: 29th Floor roof slab casted, 30th Floor structure work in progress.

Tower-5: 3rd Basement roof slab casted, 2nd Basement structure work in progress.

Tower-6: 2nd Basement roof slab casted, 1st Basement structure work in progress.

Tower-7: 2nd Basement roof slab casted, 1st Basement structure work in progress.