Construction Update
JANUARY 2026

Tower 1
Structure work Complete.
Plumbing Internal: 85% complete
Plumbing External: 75% complete
Fire Fighting: 80% complete
Tile work: 55% complete
Marble Flooring: 90% complete
Door Frames: 85% complete
PoP work: 80% complete
HVAC work: 75% complete

Tower 2
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 85% complete
Fire Fighting: Complete
Tile work: 70% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 90% complete
HVAC work: 90% complete

Tower 3
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: Complete
Fire Fighting: Complete
Tile work: 90% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 90% complete
HVAC work: Complete

Tower 4
Structure work at 18th floor in progress.


Tower 5
Structure work Complete.
Plumbing Internal: 50% complete
Plumbing External: 30% complete
Fire Fighting: 40% complete
Tile work: 30% complete
Marble Flooring: 80% complete
Door Frames: 35% complete
PoP work: 80% complete
HVAC work: 40% complete

Tower 6
Structure work Complete.
Plumbing Internal: 80% complete
Plumbing External: 50% complete
Fire Fighting: 70% complete
Tile work: 70% complete
Marble Flooring: 85% complete
Door Frames: 60% complete
PoP work: 80% complete
HVAC work: 70% complete



Tower 7
Structure work Complete.
Plumbing Internal: 85% complete
Plumbing External: 75% complete
Fire Fighting: 50% complete
Tile work: 40% complete
Marble Flooring: 60% complete
Door Frames: 60% complete
PoP work: 70% complete
HVAC work: 40% complete
Tower 8
Structure work at 15th floor in progress.
Tower 9
Structure work at 10th floor in progress.



Tower 10
Structure work at 1st floor in progress.