Construction Update
OCTOBER 2025

Tower 1
Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 50% complete
Fire Fighting: 50% complete
Tile work: 45% complete
Marble Flooring: 70% complete
Door Frames: 80% complete
PoP work: 70% complete
HVAC work: 50% complete

Tower 2
Structure work Complete.
Plumbing Internal: 95% complete
Plumbing External: 75% complete
Fire Fighting: 80% complete
Tile work: 60% complete
Marble Flooring: 80% complete
Door Frames: 95% complete
PoP work: 80% complete
HVAC work: 75% complete

Tower 3
Structure work Complete.
Plumbing Internal: Complete
Plumbing External: 90% complete
Fire Fighting: Complete
Tile work: 90% complete
Marble Flooring: Complete
Door Frames: Complete
PoP work: 90% complete
HVAC work: 90% complete

Tower 4
Structure work at 12th floor in progress.
Tower 5
Structure work Complete, Finishing work started.


Tower 6
Structure work Complete.
Plumbing Internal: 40% complete
Plumbing External: 20% complete
Fire Fighting: 45% complete
Tile work: 40% complete
Marble Flooring: 60% complete
Door Frames: 25% complete
PoP work: 60% complete
HVAC work: 25% complete

Tower 7
Structure work Complete.
Plumbing Internal: 75% complete
Plumbing External: 40% complete
Fire Fighting: 10% complete
Tile work: 20% complete
Marble Flooring: 35% complete
Door Frames: 25% complete
PoP work: 50% complete
HVAC work: 15% complete



Tower 8
Structure work at 9th floor in progress.
Tower 9
Structure work at 4th floor in progress.
Tower 10
Structure work at Upper Ground floor in progress.