Construction Update
November 2022


Tower 3 - 26th floor roof slab has been casted, 27th Floor work in progress

Tower 2 - Back Side Elevation, 6th Floor work in progress

Tower-5, Raft Casted, 3rd Basement column casting work in progress

Tower -6 raft casted and work in progress in 3rd basement

Tower 7 - Raft and 3rd basement roof slab casted, work in progress in the 2nd basement